Past Experiences

Year Client Location Description
1992 PT. PANCA USAHA PALOPO PLYWOOD Palopo 1 unit 20 T/H x 16 Bar Saturated Steam 100% Waste Wood Fired Boiler
1992 PT. BASIRIH INDUSTRIAL CORPORATION Banjarmasin 1 unit 20 T/H x 16 Bar Saturated Steam 100% Waste Wood Fired Boiler
1993 PT. PRABU ALASKA Fak-Fak, Irian Jaya 1 Unit 35 T/H x 16 Bar Saturated Steam 100% Waste Wood Fired Boiler
1994 PT. PUTRA SUMBER UTAMA TIMBER Jambi 1 Unit 20 T/H x 16 Bar Saturated Steam 100% Waste Wood Fired Boiler
1994 PT. HENDRATNA PLYWOOD Banjarmasin 1 Unit 35 T/H x 39 Bar x 450 C 50% Coal & 50% Waste Wood Fired Boiler
1994 PT. WIJAYA TRI-UTAMA PLYWOOD Banjarmasin 2 Units 35 T/H x 39 Bar x 450 C 50% Coal & 50% Waste Wood Fired Boiler & 1 Unit 6 MW CO-Generation Plant
1995 PT. PRABU ALASKA Fak-Fak, Irian Jaya 1 Unit 35 T/H x 16 Bar Saturated Steam 100% Waste Wood Fired Boiler
1995 PT. RIMBA KAYU ARTHAMAS Fak-Fak, Irian Jaya 1 Unit 35 T/H x 25 Bar x 400 C 100% Waste Wood Fired Boiler & 1 Unit N3 ? 3 MW CO-Generation Plant
1996 PT. JAYA KERTAS Kertasono 3 Units 35 T/H x 39 Bar x 450 C 100% Coal Fired Boiler
1996 PT. SOLA GRATIA PLYWOOD Pekanbaru 5 Units 10 T/H x 39 Bar x 450 C 100% Waste Wood Fired Boiler & 1 Unit B3 T/G Power Plant
1996 PT. WANA SARI Pekanbaru 2 Units 10 T/H x 39 Bar x 450 C 100% Palm Oil Fiber Boiler
1996 PT. INTRACAWOOD MANUFACTURING Tarakan 1 Unit 10 T/H x 16 Bar Saturated Steam 100% Waste Wood Fired Boiler
1996 PT. PUTRA SUMBER KREASITAMA Jambi 1 Unit 20 T/H x 16 Bar Saturated Steam 100% Waste Wood Fired Boiler
1996 PT. WIJAYA TRI-UTAMA PLYWOOD Banjarmasin 1 unit 35 T/H x 39 Bar x 450 C 50% Coal & 50% Waste Wood Fired Boiler & 1 Unit 6 MW CO-Generation Plant
1997 PT. PANCA USAHA PALOPO PLYWOOD Palopo 1 Unit 20 T/H x 16 Bar Saturated Steam 100% Waste Wood Fired Boiler
1998 PT. NAVATANI PERSADA Banjarmasin 1 Unit 20 T/H x 16 Bar Saturated Steam 100% Waste Wood Fired Boiler
1998 PT. BASIRIH INDUSTRIAL CORPORATION Banjarmasin 1 Unit 20 T/H x 16 Bar Saturated Steam 100% Waste Wood Fired Boiler
2001 SHIN YANG WOOD SYSTEM SDN.BHD Sarawak, Malaysia 1 Unit 20 T/H x 16 Bar Saturated Steam 100% Waste Wood Fired Boiler
2001 PT. WIJAYA TRI-UTAMA PLYWOOD Banjarmasin 1 Unit 3 MW Back Pressure Steam Turbine
2002 SHIN YANG WOOD SYSTEM SDN.BHD Sarawak, Malaysia 1 unit 35 T/H x 39 Bar x 450 C 100% Waste Wood Fired Boiler & 1 Unit 4 MW Extraction Condensing Steam Turbine
2002 SHIN YANG WOOD SYSTEM SDN.BHD Sarawak, Malaysia 1 unit 45 T/H x 39 Bar x 450 C 100% Waste Wood Fired Boiler & 1 Unit 7 MW Extraction Condensing Steam Turbine
2004 PT. INDO PUSAKA BERAU Berau, Kaltim 2 Units x 39 Bar x 450 C 100% Waste Wood Fired Boiler & 2 Units x 7 MW Condensing Steam Turbine
2004 PT. PURA BARUTAMA Kudus, Jateng 2 Units x 40 T/H x 39 Bar x 450 C 100% Waste Wood Fired Boiler & 2 Units x 7.5 MW Condensing Steam Turbine
2005 SHIN YANG WOOD SYSTEM SDN.BHD Sarawak, Malaysia 1 unit 45 T/H x 39 Bar x 450 C 100% Waste Wood Fired Boiler & 1 Unit 7 MW Extraction Condensing Steam Turbine
2005 FORESCOM PLYWOOD SDN. BHD Sarawak, Malaysia 1 unit 45 T/H x 39 Bar x 450 C 100% Waste Wood Fired Boiler & 1 Unit 7 MW Extraction Condensing Steam Turbine
2005 PT. PERMATA DUNIA SUKSES UTAMA Cilegon, Jabar 2 Units 45 T/H x 39 Bar x 450 C 100% Coal Fired Boiler 1 Unit 6 MW Back Pressure Steam Turbine
2006 PT. PANASIA GROUP Bandung, Jabar 2 Units 90 T/H x 54 Bar x 540 C 100% Coal Fired Boiler 1 Unit 30 MW Extraction Condensing Steam Turbine
2006 PT. CANANG INDAH Medan, Sumatera 2 Units 40 T/H x 39 Bar x 450 C Coal & Waste Wood & Fiber Fired Boiler & 2 Unit x 7 MW Condensing Steam Turbine
2006 PT. KALIMANTAN POWERINDO Samarinda, Kaltim 2 Units 50 T/H x 39 Bar x 450 C Coal & Waste Wood Fired Boiler & 2 Unit x 7.5 MW Extraction Condensing Steam Turbine
2006 PT. HARJOHN TIMBER Pontianak, Kalbar 1 Units 50 T/H x 39 Bar x 450 C Coal & Waste Wood Fired Boiler & 1 Unit x 7.5 MW Extraction Condensing Steam Turbine
2007 PT. PUSAKA JAYA PALU POWER Palu, Sulawesi 2 Units 75 T/H x 54 Bar x 540 C 100% Coal Fired Boiler 2 Unit x 15 MW Condensing Steam Turbine
2007 PT. IDEC ABADI Tarakan, Kaltim I Units 50 T/H x 39 Bar x 450 C Coal & Waste Wood Fired Boiler & 1 Unit x 4 MW Extraction Condensing Steam Turbine
2007 PT. KALIMANTAN POWERINDO Samarinda, Kaltim 2 Units 50 T/H x 39 Bar x 450 C Coal & Waste Wood Fired Boiler & 1 Unit x 7.5 MW Extraction Condensing Steam Turbine
2009 PT. KARYA PUTRA POWERIN Sampit, Kalteng 2 Units 40 T/H x 39 Bar x 450 C 100% Coal Fired Boiler 2 Unit x 7 MW Condensing Steam Turbine
2009 PT. MAHAJAYA ARYA SATYA Tanah Grogot, Samarinda 2 Units 40 T/H x 54 Bar x 485 C 100% Coal Fired CFB Boiler & 2 Unit x 7 MW Condensing Steam Turbine
2010 PT. EVERGREEN INTERNATIONAL PAPER Medan, Sumatera 2 Units 40 T/H x 39 Bar x 450 C 100% Coal Fired CFB Boiler & 1 Unit x 7.5 MW Extraction Steam Turbine
2010 PT. MEGA SURYA ERATAMA Mojokerto, Jatim 2 Units 50 T/H x 54 Bar x 485 C 100% Coal Fired CFB Boiler & 2 Unit x 7.5 MW Extration Condensing Steam Turbine
2010 PT. POLYCHEM INDONESIA tbk. Merak, Jateng 3 Units 75 T/H x 54 Bar x 540 C 100% Coal Fired CFB Boiler & 2 Unit x 15 MW Condensing Steam Turbine
2011 PT. KERTAS LECES Probolinggo, Jatim 2 Units 120 T/HR x 44 Bar x 440 C 100% Coal Fired CFB Boiler
2011 PT. TARAHAN BUKIT ASAM Tarahan, Lampung 2 Units 45 T/H x 53 Bar x 485 C 100% Coal Fired CFB Boiler 2 units x 8 MW Consending Steam Turbine
2011 PT. KARIANGAU POWER PLANT Balikpapan, Kalimantan 3 units 75T/H x 54 Bar x 540 C 100% Coal Fired CFB Boiler 2 units x 15 MW Condensing Steam Turbine